Moving procedures to new panel for full mechanized longwall equipment in GLI Omerler underground coal mine


Akdas H., Celik R.

20th International Mining Congress and Exhibition of Turkey (IMCET 2007), Ankara, Türkiye, 6 - 08 Haziran 2007, ss.39-47, (Tam Metin Bildiri)

  • Yayın Türü: Bildiri / Tam Metin Bildiri
  • Cilt numarası:
  • Basıldığı Şehir: Ankara
  • Basıldığı Ülke: Türkiye
  • Sayfa Sayıları: ss.39-47
  • Eskişehir Osmangazi Üniversitesi Adresli: Hayır

Özet

In this paper, firstly, the moving procedures of the full mechanized longwall equipment, in GLI Omerler Underground Coal Mine, to a new panel are introduced. The moving procedures have been examined in three main steps, which are preparation activities, dismantling - withdrawal of the equipment, moving and mounting activities in the new panel. Also, technical problems encountered during the moving of such complicated equipment have been mentioned. The currently employed dismantling - withdrawal practice is being realized under poor roof conditions and in the presence of high water income, causing some technical problems. Finally, considering the problems briefly mentioned above, it is suggested that a new method for the preparation and a new dismantling - withdrawal should be employed.